Two-day agenda (coach)
All coach pagesSource on GitHub
The challenge minutes are effort targets, not a serial schedule. The platform foundation is built before the event: ALZ-lite at Step 2 (T-7) and vending at Step 4 (T-1), so Day 1 opens with a 30-minute PowerPoint introduction by the tech lead, starts C1 at 09:00, and runs C2 as a 45-minute member challenge testing AI coding agents against repository and landing-zone guardrails on vm-dev01. SQL Managed Instance provisioning overlaps the start of C6, and the MI link starts on Day 2 at 08:30 while C6 finishes. The challenge totals are 10 challenges and 750 minutes.
Staff at least one coach per six attendees. Before kickoff, read the guide’s kickoff duties, lifeline handout rules and escalation table. The platform pipeline, cost estimate and cleanup are the operational references. Use Lifelines, Curveballs and APEX demo script in the Coach sidebar during the event.
Before the event
| When | Activity | Owner |
|---|---|---|
| T-30 to T-14 | Event-owner setup: choose Path A (self-service teams) or Path B (lead-provisioned cohort, with 3-to-5-person breakout pods and pod leads when n > 5), tenant and subscription access, nominate the team lead, and book the Privileged Role Administrator for T-7 (see the guide) | Event owner, team lead |
| Step 1 (T-14) | Path A: repo setup and preflight; each member shares subscription ID, index, object ID and email privately with the team lead. Path B: team lead runs Initialize-CohortRepos.ps1 and cohort whatif; students share GitHub usernames privately and accept repo invites | Team lead, members |
| Step 2 (T-7) | Bootstrap the Entra reader group, run foundation (ALZ-lite, pipeline run 1), then grant SQL MI directory read | Authorized Entra operator, team lead, Privileged Role Administrator |
| Step 3 (T-3) | Path A: each member runs whatif and member (datacenter, Test-Datacenter.ps1 before Arc, Arc onboarding). Path B: team lead runs member across the cohort. Everyone completes the portal migration assessment, vm-dev01 Copilot setup and factory/evidence/readiness/ | Team lead, members |
| Step 4 (T-1) | Sync the reader group from the full private roster, then vend (in batches such as -f members=1-50 when n > 60). Vending stops at the first unready member; earlier members are vended but not restarted, exempted or probed, and later members are not vended | Group owner, team lead |
| Before Day 1 | Start both VMs of every datacenter (idle ones may have been stopped), check the room and projection, stage demo materials and publish this agenda | Event owner, coaches |
Day 1
| Time | Activity | Challenge / owner | Notes |
|---|---|---|---|
| 08:30–09:00 | 30-minute kickoff presentation (scenario, roles, challenges) and roster lock | Kickoff / tech lead and event owner | Include two or three full-ALZ slides or a short recording to contrast the production pattern with ALZ-lite; no separate live ALZ demo. The owner supplies this material before the event. The roster locks here |
| 09:00–09:45 | Define the opportunity (CAF Strategy) | C1 / teams | Everyone starts here, team lead included. C1 needs no Azure access |
| 09:45–10:30 | Secure, AI-ready foundation (AI guardrails test) | C2 / members | Each member tests an AI coding agent against APEX’s Bicep baseline (iac-security-baseline.md) and ALZ Deny policies in rg-spoke, checks exemptions and runs Test-Connectivity.ps1 |
| 10:15 (inside C2) | Day 1 policy curveball | Coach, team lead | Follow Curveballs in the Coach sidebar; capture the denial and decision, then remove only the exercise assignment before C5 at 13:45 |
| 10:30–11:30 | Assess the source | C3 / members | Each member runs the Upgrade agent assessment and plan on vm-dev01 and triages the Arc SQL assessment findings |
| 11:30–12:15 | Choose target states | C4 / teams | Complete decisions-and-register.md in the team/pod lead’s repo |
| 12:15–13:15 | Lunch break | — | — |
| 13:15–13:45 | APEX archetype demo | C5 / coach | Use the 30-minute script; show APEX’s artifact/review flow and the azd deployment path |
| 13:45–14:45 | Deploy the CoE archetype | C5 / members | Adapt, preview, provision and document the deployed state |
| 14:45–16:15 | Modernize with GitHub Copilot, part 1 | C6 / members | MI provisioning starts in the background; do not deploy the app to App Service yet |
| 16:15–16:30 | Break | — | — |
| 16:30–16:45 | Day 1 check-out and evidence capture | Event owner, coaches | If the Day 1 deny-policy curveball ran during C2, confirm curveball-allowed-locations was removed before C5 started. Leave both VMs running |
Day 2
| Time | Activity | Challenge / owner | Notes |
|---|---|---|---|
| 08:30–09:00 | Reconnect, check both VMs are running and the Graph grant is done, then start the MI link | Team lead, members | The link is C7 requirements 1 and 2 (prepare the source, then start the link), started early so seeding overlaps the end of C6. Requirements 1 and 2 count toward C7’s 120 minutes, but the wait of up to 10 minutes while the link is created overlaps C6 and doesn’t count |
| 09:00–10:30 | Modernize with GitHub Copilot, part 2 | C6 / members | Complete the 180-minute total across both days |
| 10:30–12:30 | Migrate and go live | C7 / members | About 100 minutes of C7’s 120-minute effort remain after the early link setup. This window includes seeding slack; do not skip go/no-go. Trigger the abort curveball at go/no-go |
| 12:30–13:15 | Lunch break | — | — |
| 13:15–14:00 | Validate the pattern | C8 / members | Smoke, load, security (acceptance.json), upload, notification and telemetry checks on vm-dev01 |
| 14:00–15:00 | Optimize the database with GitHub Copilot | C9 / members | Query Store baseline vs after and 5 .sql fix scripts |
| 15:00–15:15 | Break | — | — |
| 15:15–16:15 | Package, hand over and review AI readiness | C10 / teams | Complete reusable-asset/ and handover-and-ai-review.md in the team/pod lead’s repo |
| 16:15–17:00 | Showcase and close | Event owner, coaches, teams | 5-minute team showcases and owner follow-ups |
Planned overlaps and controls
- ALZ-lite is deployed at Step 2 (T-7) and every member is vended at Step 4 (T-1), so the foundation and spokes are already in place when Day 1 begins.
- SQL MI provisioning starts while C6 begins on Day 1. The MI link starts at 08:30 on Day 2 (C7 requirements 1 and 2), so automatic seeding runs while the final C6 work completes.
- Keep
vm-dev01running from Day 1 kickoff to the end of the event, and keepvm-app01running until the link is removed. Stop VMs only in the gaps before the event (not during the Step 4 vending, which restarts and probes them) and after the event. - If the MI or link misses the agenda window, do not skip the read-only replica checks or cut over under time pressure. The coach uses the Day 2 abort curveball and the team replans.
- The morning schedule on Day 1 is sequential (kickoff 08:30, C1 09:00, C2 09:45, C3 10:30, C4 11:30), so the team lead and members move through C1 to C4 together without splitting tracks.
- Teams take a 10 to 15 minute break inside their own time box when needed. Move showcase discussion rather than silently extending the challenge time boxes.