Two-day agenda (coach)

The challenge minutes are effort targets, not a serial schedule. The platform foundation is built before the event: ALZ-lite at Step 2 (T-7) and vending at Step 4 (T-1), so Day 1 opens with a 30-minute PowerPoint introduction by the tech lead, starts C1 at 09:00, and runs C2 as a 45-minute member challenge testing AI coding agents against repository and landing-zone guardrails on vm-dev01. SQL Managed Instance provisioning overlaps the start of C6, and the MI link starts on Day 2 at 08:30 while C6 finishes. The challenge totals are 10 challenges and 750 minutes.

Staff at least one coach per six attendees. Before kickoff, read the guide’s kickoff duties, lifeline handout rules and escalation table. The platform pipeline, cost estimate and cleanup are the operational references. Use Lifelines, Curveballs and APEX demo script in the Coach sidebar during the event.

Before the event

WhenActivityOwner
T-30 to T-14Event-owner setup: choose Path A (self-service teams) or Path B (lead-provisioned cohort, with 3-to-5-person breakout pods and pod leads when n > 5), tenant and subscription access, nominate the team lead, and book the Privileged Role Administrator for T-7 (see the guide)Event owner, team lead
Step 1 (T-14)Path A: repo setup and preflight; each member shares subscription ID, index, object ID and email privately with the team lead. Path B: team lead runs Initialize-CohortRepos.ps1 and cohort whatif; students share GitHub usernames privately and accept repo invitesTeam lead, members
Step 2 (T-7)Bootstrap the Entra reader group, run foundation (ALZ-lite, pipeline run 1), then grant SQL MI directory readAuthorized Entra operator, team lead, Privileged Role Administrator
Step 3 (T-3)Path A: each member runs whatif and member (datacenter, Test-Datacenter.ps1 before Arc, Arc onboarding). Path B: team lead runs member across the cohort. Everyone completes the portal migration assessment, vm-dev01 Copilot setup and factory/evidence/readiness/Team lead, members
Step 4 (T-1)Sync the reader group from the full private roster, then vend (in batches such as -f members=1-50 when n > 60). Vending stops at the first unready member; earlier members are vended but not restarted, exempted or probed, and later members are not vendedGroup owner, team lead
Before Day 1Start both VMs of every datacenter (idle ones may have been stopped), check the room and projection, stage demo materials and publish this agendaEvent owner, coaches

Day 1

TimeActivityChallenge / ownerNotes
08:30–09:0030-minute kickoff presentation (scenario, roles, challenges) and roster lockKickoff / tech lead and event ownerInclude two or three full-ALZ slides or a short recording to contrast the production pattern with ALZ-lite; no separate live ALZ demo. The owner supplies this material before the event. The roster locks here
09:00–09:45Define the opportunity (CAF Strategy)C1 / teamsEveryone starts here, team lead included. C1 needs no Azure access
09:45–10:30Secure, AI-ready foundation (AI guardrails test)C2 / membersEach member tests an AI coding agent against APEX’s Bicep baseline (iac-security-baseline.md) and ALZ Deny policies in rg-spoke, checks exemptions and runs Test-Connectivity.ps1
10:15 (inside C2)Day 1 policy curveballCoach, team leadFollow Curveballs in the Coach sidebar; capture the denial and decision, then remove only the exercise assignment before C5 at 13:45
10:30–11:30Assess the sourceC3 / membersEach member runs the Upgrade agent assessment and plan on vm-dev01 and triages the Arc SQL assessment findings
11:30–12:15Choose target statesC4 / teamsComplete decisions-and-register.md in the team/pod lead’s repo
12:15–13:15Lunch break——
13:15–13:45APEX archetype demoC5 / coachUse the 30-minute script; show APEX’s artifact/review flow and the azd deployment path
13:45–14:45Deploy the CoE archetypeC5 / membersAdapt, preview, provision and document the deployed state
14:45–16:15Modernize with GitHub Copilot, part 1C6 / membersMI provisioning starts in the background; do not deploy the app to App Service yet
16:15–16:30Break——
16:30–16:45Day 1 check-out and evidence captureEvent owner, coachesIf the Day 1 deny-policy curveball ran during C2, confirm curveball-allowed-locations was removed before C5 started. Leave both VMs running

Day 2

TimeActivityChallenge / ownerNotes
08:30–09:00Reconnect, check both VMs are running and the Graph grant is done, then start the MI linkTeam lead, membersThe link is C7 requirements 1 and 2 (prepare the source, then start the link), started early so seeding overlaps the end of C6. Requirements 1 and 2 count toward C7’s 120 minutes, but the wait of up to 10 minutes while the link is created overlaps C6 and doesn’t count
09:00–10:30Modernize with GitHub Copilot, part 2C6 / membersComplete the 180-minute total across both days
10:30–12:30Migrate and go liveC7 / membersAbout 100 minutes of C7’s 120-minute effort remain after the early link setup. This window includes seeding slack; do not skip go/no-go. Trigger the abort curveball at go/no-go
12:30–13:15Lunch break——
13:15–14:00Validate the patternC8 / membersSmoke, load, security (acceptance.json), upload, notification and telemetry checks on vm-dev01
14:00–15:00Optimize the database with GitHub CopilotC9 / membersQuery Store baseline vs after and 5 .sql fix scripts
15:00–15:15Break——
15:15–16:15Package, hand over and review AI readinessC10 / teamsComplete reusable-asset/ and handover-and-ai-review.md in the team/pod lead’s repo
16:15–17:00Showcase and closeEvent owner, coaches, teams5-minute team showcases and owner follow-ups

Planned overlaps and controls

  • ALZ-lite is deployed at Step 2 (T-7) and every member is vended at Step 4 (T-1), so the foundation and spokes are already in place when Day 1 begins.
  • SQL MI provisioning starts while C6 begins on Day 1. The MI link starts at 08:30 on Day 2 (C7 requirements 1 and 2), so automatic seeding runs while the final C6 work completes.
  • Keep vm-dev01 running from Day 1 kickoff to the end of the event, and keep vm-app01 running until the link is removed. Stop VMs only in the gaps before the event (not during the Step 4 vending, which restarts and probes them) and after the event.
  • If the MI or link misses the agenda window, do not skip the read-only replica checks or cut over under time pressure. The coach uses the Day 2 abort curveball and the team replans.
  • The morning schedule on Day 1 is sequential (kickoff 08:30, C1 09:00, C2 09:45, C3 10:30, C4 11:30), so the team lead and members move through C1 to C4 together without splitting tracks.
  • Teams take a 10 to 15 minute break inside their own time box when needed. Move showcase discussion rather than silently extending the challenge time boxes.