Readiness check (coach)

Coach and team-lead reference. No coach is on duty during the pre-hackathon window; support before day one is best-effort and attendees contact their designated team lead first. Attendees follow the numbered steps in Step 3: Datacenter and workstation and Step 4: Vending.

The readiness setup has no points. In Path A (Self-service teams), each member runs Step 1 (T-14) and Step 3 (T-3) in their own repository against their own workload subscription. In Path B (Lead-provisioned cohort), the team lead creates the student repositories (Initialize-CohortRepos.ps1) and runs whatif and member across the cohort from the lead repository (batching -f members=1-250 when n > 256), while attendees complete Student onboarding. At T-1 (Step 4), the team lead runs the vending stage across the roster (batching -f members=1-50 when n > 60): Invoke-PipelineVending.ps1 automatically checks that each member’s vnet-datacenter exists and vm-app01 is Connected in Azure Arc before vending their spoke.

If a coach is reviewing readiness evidence at kickoff on day one (or helping a team lead troubleshoot a member before T-1), use the checklist below.

Find the blocker

  • Preflight isn’t green. Check the whatif or member run summary for the first failed check. Resolve the preflight failure.
  • Vending stopped or finished with errors. Check the phase and the member indexes in the run summary. Find which members to rerun.
  • Arc is connected but no SQL instance appears. Check the SQL Server extension on vm-app01. See the Arc and extension hints before rerunning anything.
  • Bastion or Copilot isn’t ready. Check whether vm-dev01 is running and whether the member can sign in to GitHub from VS Code. Troubleshoot the workstation.
  • A member’s datacenter needs rebuilding. Check whether Arc onboarding started and whether the member has reached C5. Use the matching recovery path; don’t redeploy an Arc-connected datacenter.

How readiness is verified

  1. Automated check in Step 4 (vending at T-1): for each member in roster.json, Invoke-PipelineVending.ps1 verifies that vnet-datacenter exists in rg-datacenter and that the Azure Arc machine vm-app01 has properties.status == 'Connected'. Because the member stage only runs Connect-DatacenterArc.ps1 after Test-Datacenter.ps1 passes all checks, an Arc Connected status proves the datacenter deployed and passed the pre-Arc validation.
  2. Evidence in factory/evidence/readiness/: each member commits their readiness artifacts to main in their own repository during Step 3.
  3. Vending failures: if phase 1 stops at the first unready member, earlier members are vended but not restarted, exempted or probed, and later members are not vended. Fix the cause and rerun vending for all members; it is safe to repeat. If phase 2 fails while restarting VMs, fix the cause and rerun for all members. If phase 3 names members whose exemptions or connectivity probes failed, rerun only for those named indexes.
  4. Datacenter redeploy: a datacenter redeployed after vending requires vending again (see Recovery).

Readiness checklist

Use this list when spot-checking factory/evidence/readiness/ in a member’s repository at kickoff or when helping a team lead unblock a member.

  • Preflight is green. Check the whatif or member job log for the GO verdict. Get-PipelineEvidence.ps1 saves only test-datacenter.txt. A GO verdict does not cover the manual checks: MFA, GitHub Copilot, GitHub repositories and Azure Hybrid Benefit.
  • Test-Datacenter.ps1 PASS from before Arc onboarding: all green, including the perf kit’s planted objects and data present on vm-app01’s SQL Server (C9 depends on them: if they’re missing, the perf kit needs resetting before C9). It can’t pass after Arc onboarding, so don’t ask for a re-run. The member stage runs the test first and onboards Arc only if it passes, so a pipeline member can’t hit the order mistake. The run summary, or evidence/readiness/test-datacenter.txt from Get-PipelineEvidence.ps1, counts as this output.
  • Arc connected: the Arc resource for vm-app01 shows Connected (Invoke-PipelineVending.ps1 checks this automatically), with the SQL Server extension installed and the instance listed.
  • Arc assessment output: a screenshot or export of the first Arc migration assessment. They don’t need to have acted on it, because C3 is where that happens. If the assessment isn’t available yet (Arc’s own assessment feature is still initializing), accept the pre-Arc Test-Datacenter.ps1 green output and have the member pull the assessment first thing in C3.
  • Hybrid Benefit and cost check: the member confirms Azure Hybrid Benefit is on (or gives the reason it isn’t), confirms per-user Windows 11 multitenant hosting rights for vm-dev01, and says what state the VMs are in. A member without eligible Windows Server licenses used -f no-hybrid-benefit=true; vm-app01 then bills about $0.37 an hour more (about $1.92 instead of $1.55 an hour while running; estimate checked 2026-10-08).
  • The credentials file: Get-PipelineEvidence.ps1 writes .local/<subscription-id>/datacenter.json with the documented fixed lab credentials, because the runner deployed the datacenter. Later password lookups (the vm-dev01 setup, C7 to C9) read it. If the file is missing, have them run the script again.
  • Evidence in evidence/readiness: the member’s own repo holds the files on main, in factory/evidence/readiness/.
  • vm-dev01 and Copilot validated: a screenshot of Copilot Chat answering in VS Code on vm-dev01, signed in to GitHub. If it’s missing or Copilot is blocked, it’s a blocker: C3 and C6 depend on it, so fix the access before C3.

How members get there

In Path A, members run the readiness stages from GitHub Actions in their own repo using the settings registered with the pipeline (member steps), and the team lead runs their own datacenter in the lead repo with -f members=1. In Path B, the team lead dispatches whatif, member and vending for all n cohort indexes from the lead repo, and students complete Student onboarding in their pre-created repo and on vm-dev01.

With required reviewers enabled, approvals apply to jobs, not once per stage. whatif has preflight, plus ALZ-lite what-if in the lead profile. member has preflight, then the member matrix. foundation and vending each have one job. all has preflight, ALZ-lite what-if, foundation, the member matrix and vending in sequence. teardown has the member matrix, then team cleanup only for an explicitly confirmed full lead teardown. Matrix jobs can appear together in one approval prompt; approve only the named, intended jobs.

  1. gh workflow run platform.yml -f stage=whatif: the preflight, with -Fix (the lead’s run also does the ALZ-lite what-if). The member reviews the manual-check list it prints and confirms each one.
  2. gh workflow run platform.yml -f stage=member -f members=<index>: deploys the datacenter, runs Test-Datacenter.ps1 with both VMs running, and only if that passes onboards vm-app01 to Azure Arc. The test comes before Arc because after Arc, run commands on vm-app01 stop working and the in-VM checks fail. There is no portal fallback for Arc, by design.
  3. ./scripts/Get-PipelineEvidence.ps1 downloads the Test-Datacenter.ps1 output into evidence/readiness/ and writes the credentials file. The member commits the evidence file.
  4. In the Arc resource’s SQL Server blade, the member starts (or reviews) the migration assessment.
  5. The member connects to vm-dev01 through Bastion, opens VS Code, signs in to GitHub and sends a message in Copilot Chat.
  6. Before the event, the member may stop both VMs (vm-app01, vm-dev01) when not working, and must start them again before the vending stage at T-1, because vending restarts both and the probes run inside them. During the event, never stop vm-dev01.

The manual path, for repairs only, is on the deploy with scripts page. Students never run it.

Hints

  • Ask each member to confirm the partner GitHub organization has included Actions compute available and a payment method for additional private-repo usage. The repository owner is billed; check Billing & Licensing, the budget and payment method before preflight.
  • Running preflight once and not re-running the whatif stage after resource provider registration (which takes up to 15 minutes to propagate) leaves a false red.
  • Trying a manual Arc onboarding through the portal “just to see” works but produces a differently named Arc resource that later scripts (Test-Datacenter.ps1, the migration assessment lookups) won’t find. Redo it with the script if this happened.
  • Turning Azure Hybrid Benefit off during the event: it should stay on throughout. A member without eligible Windows Server licenses must set no-hybrid-benefit=true on the initial member stage, before Arc onboarding.
  • Leaving both VMs running between sessions isn’t a correctness problem, but it bills for nothing, so remind members. Stopping vm-dev01 during the event is the opposite mistake: it’s the members’ workstation.
  • Arc Connected but no SQL Server instance after 5 minutes on an older copy of the kit: install the WindowsAgent.SqlServer extension from the portal (Azure Arc > Machines > vm-app01 > Extensions). The current script installs it after 5 minutes (see platform pipeline).
  • Arc onboarding before Test-Datacenter.ps1 is only possible in a hand-run repair. The in-VM rows can’t pass after Arc. Accept the in-VM FAIL, with the member’s written explanation, if every Azure-side row (the ones that start with azure:: VM state, size and license type, Trusted Launch, disks, no public IPs, Bastion) is green and Arc shows Connected with the SQL instance. Redo only if an Azure-side row fails: that means the datacenter itself is wrong. The perf kit’s planted data can’t be checked after Arc, so look at it at the start of C9.
  • Preflight and datacenter deployed, but Arc onboarding not finished: vending refuses to vend that member until vm-app01 shows Connected in Azure Arc. Once the member finishes onboarding, the team lead reruns vending for all members; it is safe to repeat.

Recovery

Rerunning the member stage is safe before Arc onboarding: it redeploys the datacenter with the same parameters, and the stage refuses to redeploy over Arc. There is no -Force parameter. After Arc onboarding, use the recovery below.

  • Arc-enabled, before C5: there is no in-place reset. To recover, run teardown, then member. In the member’s own repo (member profile), run:

    Terminal window
    gh workflow run platform.yml -f stage=teardown
    gh workflow run platform.yml -f stage=member

    In the team lead’s repo, run the same stages with the member’s index:

    Terminal window
    gh workflow run platform.yml -f stage=teardown -f members=<your index>
    gh workflow run platform.yml -f stage=member -f members=<your index>

    Member teardown removes rg-datacenter, rg-spoke and the archetype, including the SQL Managed Instance. Repeat Step 3 and the vm-dev01 setup. If the member does not hold eligible Windows Server licenses, add -f no-hybrid-benefit=true to the member command. If the member was already vended, the team lead runs vending for that index afterward. Before T+2, never run a full, unfiltered teardown in the team lead’s repo; pass -f members=<your index> or ask the event owner for a coach repair. After C5, do not use this recovery; ask the event owner for a coach repair.

  • A run that can’t be repaired in time: a coach runs the scripts by hand, from the commands on the deploy with scripts page. Never rerun Arc, and never redeploy the datacenter after Arc.